Question 1

Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

  1. Change requests
  2. Earned value management results
  3. Stakeholder analysis plan
  4. Performance reports
Show answer and explanation

Correct answer: D. Performance reports

Information distribution takes the communications management plan, performance reports, and organizational process assets as its inputs. Performance reports are what carry status, progress, and forecast information to the 121 stakeholders, so they must be available before information can be distributed. Without them the plan describes how to communicate but there is nothing of substance to send.

Why the other options are wrong

  • A. Change requests flow through integrated change control and are not an input to distributing information.
  • B. Earned value results are an analytical output of performance measurement that may feed a report, but they are not themselves a defined input to information distribution.
  • C. There is no stakeholder analysis plan artifact in the communications framework; stakeholder analysis informs the communications management plan, which is already in place here.

Question 2

What is the formula to determine earned value (EV) for a program?

  1. Percent complete times percent remaining in the program
  2. Percent completes time the program cost estimate
  3. Percent complete times the program budget at completion
  4. Percent complete times the program cost of labor and materials
Show answer and explanation

Correct answer: C. Percent complete times the program budget at completion

completion Earned Value (EV) is calculated by multiplying the percent of work completed by the total program budget at completion (BAC). This gives the monetary value of the work actually accomplished to date. The formula is: EV = Percent Complete × Budget at Completion.

Why the other options are wrong

  • A. Percent complete times percent remaining produces a meaningless metric unrelated to earned value.
  • B. This formula is incomplete and does not represent the standard earned value calculation.
  • D. While labor and materials are part of the budget, the correct formula uses the total program budget at completion, not just labor and materials costs.

Question 3

Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team.

This requirement for four licensed electricians is an example of which one of the following terms?

  1. Screening system
  2. Scoring model
  3. Vendor analysis requirements
  4. Evaluation criteria
Show answer and explanation

Correct answer: A. Screening system

A screening system establishes minimum, pass or fail requirements that a seller must satisfy just to remain in consideration. Requiring at least four licensed electricians is exactly that kind of threshold: a vendor either meets it or is removed from the competition before any comparative rating occurs. Olive is filtering the field, not ranking proposals.

Why the other options are wrong

  • B. A scoring model is the weighted rating method used to compare proposals that have already cleared the minimum requirements.
  • C. Vendor analysis requirements is not recognized procurement terminology.
  • D. Evaluation criteria are the broader set of factors used to assess and rank competing proposals, while this single mandatory threshold is applied to screen sellers out.

See all 10 free questions Get the full pack, US$39

713 practice questions for PMI Program Management Professional (PgMP), with full explanations.

Every question comes with the correct answer, the reasoning behind it, and a short note on why each wrong option is wrong. Work through it once with the answers, then again with the questions-only copy under exam conditions.

  • 713 questions across all five PgMP domains
  • Answers and explanations for every question, including the wrong options
  • A questions-only PDF for timed practice runs
  • Instant delivery by email the moment you check out
  • Free monthly updates for as long as the exam is live
  • Pass or your money back

This pack is US$39, paid once.

Try 10 questions free before you buy.

Last updated September 2026 · 713 questions

What makes the PgMP hard

PgMP is one of PMI’s most prestigious credentials: the programme management step above the PMP, for experienced professionals who coordinate several related projects to deliver strategic business outcomes. It carries real weight for senior programme and portfolio roles.

The exam covers managing programmes end to end: strategic alignment, benefits and business alignment, stakeholder engagement, governance, and the full programme life cycle across multiple coordinated projects. It assumes substantial real-world programme leadership, not just project management knowledge.

One domain dominates. Program life cycle management is 44% of the exam, close to half, while business alignment is only 11%. Spreading study time evenly across the five domains wastes most of it, and the sitting is long: 170 questions in 240 minutes.

About the exam

The PMI Program Management Professional (PgMP) validates advanced experience coordinating multiple related projects and their resources to achieve strategic objectives. It is intended for highly experienced programme managers, and your application goes through a panel review before you can sit the exam.

Exam domains

  • Strategic program alignment: 15%
  • Program life cycle management: 44%
  • Business alignment: 11%
  • Stakeholder engagement: 16%
  • Governance: 14%

170 questions, 240 minutes, at Pearson VUE test centres or online proctored. The certification is maintained through PMI’s continuing certification requirements.

Reviews

There are no reviews yet.

Only logged in customers who have purchased this product may leave a review.

Questions before you buy

What do I get when I buy the PMI PgMP pack?

713 practice questions as a PDF, each with the correct answer, a full explanation and a note on why the other options are wrong, plus a separate questions-only PDF for timed practice.

How quickly do I receive it?

Your PDF is prepared and sent to your email address after checkout, and you get a confirmation as soon as it is on its way.

Is there a free sample?

Yes. Ten questions from this pack, with answers and explanations, are free on this page and as a PDF, so you can judge the quality before you pay.

Are updates included?

Yes. The pack is updated every month for as long as the exam is live, and updates are free for everyone who has bought it.

What if I fail the exam?

We refund the pack. Sit the exam 7 to 30 days after buying, then send your official score report within 7 days of the exam date, as set out in the refund policy.

Can I share it with colleagues?

Each purchase is licensed to one person. For a team, school or training organisation, email support@certstash.com for a licence that fits.